These projects include projects of Generation stations, projects of transformers stations, projects of over head transmission lines and project of the under ground cables that have been done in 2004/2005.
 

Implemented Projects in 2004/2005

 

First: Power Plants

Date of Commercial Operation

Capacity (M.W)

Voltage (K.V)

Projects

July/August 2005

250x2

220

The gas part of the first stage for compound North Cairo project

   
 

Second: Transformers Plants

   
 

A.  Extra High voltage 500, 220, 132Kv (New and Extension)

Date implemented  project

Capacity (M.V.A)

Voltage (K.V)

Projects

S

6/7/2004

125

220/66/11

Expanding the substation of El-Mahala with a third transformer

1

14/7/2004

-

220

Expanding the substation Monouf with two units to join  Nubareia

2

7/8/2004

-

220/66/11

Installing a moving car at Almasaid transferred from Sharm El Sheikh, capacity 40 MWh

3

22/8/2004

150

220/132

Expanding Misr Aluminum company with a 10th transformer

4

8/9/2004

75

220/66/11

Expanding the substation, south of Malawi with a third transformer

5

29/9/2004

125

220/66/11

Expanding the substation of Nag Hamadi with a 10th  transformer

6

22/12/2004

150

220/132

Expanding Misr Aluminum company with  the 11th transformer

7

8/2/2005

75

220/66/11

Expanding the substation of Demo with a third transformer

8

20/2/2005

75

220/66/11

Expanding the substation of Riva with a third transformer

9

10/3/2005

125

220/66/11

Expanding the Karmouz transformer with a third transformer

10

29/4/2005

125

220/66/11

Expanding the substation of Heliopolis with a fourth transformer

11

31/5/2005

125x2

220/66

Kowisna Substation

12

 

1275

 Total of capacities

 

B.  Extra high voltage (Replacement)

 

Date implemented  project

Capacity (M.V.A)

Voltage (K.V)

Projects

S

8/2004

-

220

Replacing one circuit breaker (SF6) at the Ain El-Sokhna

1

9/2004

-

220

Replacing two circuit braker(SF6) at Sharm El-Sheikh

2

20/2/2005

-

220

Replacing two circuit breaker at Samalot

3

 

C.  High voltage 66 Kv (New, Expansion, and Replacement)

 

1812,5M.W.H

High voltage substation (New, Expansion )

1

159,8M.W.H

New Transformers (Replacement)

2

 

Third: Overhead Transmission Lines

A.  Extra High voltage 500, 220, 132Kv (New and Expansion)

 

End Date

Length (Km)

Voltage (K.V)

Projects

S

13/7/2004

2*2.5

220

The Overhead Transmission Line of Naga-Hammadi/Misr Aluminum.

1

15/1/2005

2*42.15

220

The Dual Overhead Transmission Line for electricity Generation in Nubareya/Menoof.

2

15/1/2005

2*56

220

The Dual Overhead Transmission Line for Electricity Generation in Nubareya/Bustan.

3

31/5/2005

2*2*2

220

Combining Tanta/Qualyobeya In-Out Line with Quesna

4

209

Total Length of All Circuits 

 

B.  High voltage 11 ,66 Kv

 

418 km

Total Length of All High Voltage Circuits

 

Fourth: Under Ground Cables

A.  Extra High voltage 220 Kv

 

2*0.375 Km

Joining the new North Cairo with the two cables of Heliopolis and Basoos

1

0.75 km

Total Length of Extra High Voltage Cables Circuits

 

B.  High voltage 66 Kv

 

134 km

Total Length of High Voltage Cables Circuits