|
A.
Extra High
voltage 500, 220, 132Kv (New and
Extension)
|
|
Date implemented project |
Capacity (M.V.A) |
Voltage (K.V) |
Projects |
S |
|
6/7/2004 |
125 |
220/66/11 |
Expanding the substation of El-Mahala with a
third transformer |
1 |
|
14/7/2004 |
- |
220 |
Expanding the substation Monouf with two units to
join Nubareia |
2 |
|
7/8/2004 |
- |
220/66/11 |
Installing a moving car at Almasaid transferred
from Sharm El Sheikh, capacity 40 MWh |
3 |
|
22/8/2004 |
150 |
220/132 |
Expanding Misr Aluminum company with a 10th
transformer |
4 |
|
8/9/2004 |
75 |
220/66/11 |
Expanding the substation, south of Malawi with a
third transformer |
5 |
|
29/9/2004 |
125 |
220/66/11 |
Expanding the substation of Nag Hamadi with a 10th
transformer |
6 |
|
22/12/2004 |
150 |
220/132 |
Expanding Misr Aluminum company with the 11th
transformer |
7 |
|
8/2/2005 |
75 |
220/66/11 |
Expanding the substation of Demo with a third
transformer |
8 |
|
20/2/2005 |
75 |
220/66/11 |
Expanding the substation of Riva with a third
transformer |
9 |
|
10/3/2005 |
125 |
220/66/11 |
Expanding the Karmouz transformer with a
third transformer |
10 |
|
29/4/2005 |
125 |
220/66/11 |
Expanding the substation of Heliopolis with a
fourth transformer |
11 |
|
31/5/2005 |
125x2 |
220/66 |
Kowisna Substation |
12 |
|
|
1275
|
Total of capacities
|
|
B. Extra
high voltage
(Replacement)
|
|
Date implemented project |
Capacity (M.V.A) |
Voltage (K.V) |
Projects |
S |
|
8/2004 |
- |
220 |
Replacing one circuit breaker (SF6) at the Ain El-Sokhna |
1 |
|
9/2004 |
- |
220 |
Replacing two circuit braker(SF6) at Sharm
El-Sheikh |
2 |
|
20/2/2005 |
- |
220 |
Replacing two circuit breaker at Samalot |
3 |
|
C.
High voltage 66
Kv (New, Expansion, and Replacement)
|
|
1812,5M.W.H |
High voltage substation (New, Expansion ) |
1 |
|
159,8M.W.H |
New Transformers (Replacement) |
2 |
|
Third: Overhead
Transmission Lines
A.
Extra High
voltage 500, 220, 132Kv (New and Expansion)
|
|
End Date |
Length (Km) |
Voltage (K.V) |
Projects |
S |
|
13/7/2004 |
2*2.5 |
220 |
The
Overhead
Transmission Line of Naga-Hammadi/Misr Aluminum. |
1 |
|
15/1/2005 |
2*42.15 |
220 |
The
Dual Overhead
Transmission Line for electricity Generation in Nubareya/Menoof. |
2 |
|
15/1/2005 |
2*56 |
220 |
The Dual Overhead
Transmission Line for Electricity Generation in Nubareya/Bustan. |
3 |
|
31/5/2005 |
2*2*2 |
220 |
Combining
Tanta/Qualyobeya In-Out Line with Quesna |
4 |
|
209 |
Total
Length of All Circuits
|
|
B. High voltage
11 ,66 Kv
|
|
418 km
|
Total Length of All High Voltage
Circuits
|
|
Fourth: Under Ground
Cables
A.
Extra High voltage 220 Kv
|
|
2*0.375 Km |
Joining the new North Cairo with the two cables
of Heliopolis and Basoos |
1 |
|
0.75 km
|
Total Length of Extra High Voltage Cables
Circuits
|
|
B.
High voltage 66 Kv
|
|
134
km
|
Total Length of High Voltage Cables Circuits
|